Risk Assessment at Workplace in Underground Lead and Zinc Mine with Application of Fuzzy Topsis Method

Stojance Mijalkovski1, *, Dragi Peltechki2, Kemajl Zeqiri3, Joze Kortnik4, Dejan Mirakovski1

Corresponding Author:

Stojance Mijalkovski

Affiliation(s):

1. Faculty of Natural and Technical Sciences, Mining Engineering, “Goce Delchev” University, Shtip, N. Macedonia
Email: [email protected], [email protected]
2. Rudplan DOOEL, Strumica, N. Macedonia
Email: [email protected]
3. Faculty of Geosciences, Department of Mining, Isa Boletini University, Mitrovice, Kosovo
Email: [email protected]
4. Faculty of Natural Sciences and Engineering, Department of Geotechnology, Mining and Environment, University of Ljubljana, Ljubljana, Slovenia
Email: [email protected]
*Corresponding Author

Abstract:

Underground mining is considered one of the most dangerous industries, because serious injuries or accidents often occur at the workplace. In recent years, fuzzy multiple criteria decision-making has found increasing application in job risk assessment, taking into account a number of influential parameters. This paper uses fuzzy TOPSIS method for workplace risk assessment in an underground lead and zinc mine, where the results are be compared with the number of injuries and accidents that have occurred in individual workplaces to assess its accuracy. Accurate workplace risk assessment in underground mines is very important so that appropriate safety measures can be taken in a timely manner to avoid injuries and deaths at work.

Keywords:

Risk assessment, workplace, underground mine, fuzzy multi-criteria decision-making, fuzzy TOPSIS

Downloads: 244 Views: 1800
Cite This Paper:

Stojance Mijalkovski, Dragi Peltechki, Kemajl Zeqiri, Joze Kortnik, Dejan Mirakovski (2020). Risk Assessment at Workplace in Underground Lead and Zinc Mine with Application of Fuzzy Topsis Method. Journal of the Institute of Electronics and Computer, 2, 121-141. https://doi.org/10.33969/JIEC.2020.21008.

References:

[1] Gul, M., Ak, M. F. and Guneri, A. F. (2019). Pythagorean fuzzy VIKOR-based approach for safety risk assessment in mine industry, Journal of Safety Research, 69, 135-153. https://doi.org/10.1016/j.jsr.2019.03.005
[2] Zeqiri, K., Kortnik, J. and Mijalkovski, S. (2020). Determination of the risk at workplace, assessment and its rank calculation, in mining activities, GeoScience Engineering, 66, 69-75. http://gse.vsb.cz/ojs/index.php/GSE/article/view/303
[3] Gul, M. and Guneri, A. F. (2016). A fuzzy multi criteria risk assessment based on decision matrix technique: A case study for aluminum industry, Journal of Loss Prevention in the Process Industries, 40, 89-100. https://doi.org/10.1016/j.jlp.2015.11.023
[4] Guneri, A.F., Gul, M. and Ozgurler, S. (2015). A fuzzy AHP methodology for selection of risk assessment methods in occupational safety, International Journal of Risk Assessment and Management, 18, 319-335. https://www.inderscience.com/info/inarticle.php?artid=71222
[5] Dhillon, B. S. (2010). Mine Safety, A Modern Approach. University of Ottawa, Canada.
[6] Marhavilas, P.K. and Koulouriotis, D.E. (2008). A risk-estimation methodological framework using quantitative assessment techniques and real accidents’ data: Application in an aluminium extrusion industry, Journal of Loss Prevention in the Process Industries, 21, 596-603. https://doi.org/10.1016/j.jlp.2008.04.009
[7] Marhavilas, P.K., Koulouriotis, D. and Gemeni, V. (2011). Risk analysis and assessment methodologies in the work sites: On a review, classification and comparative study of the scientific literature of the period 2000-2009, Journal of Loss Prevention in the Process Industries, 24, 477-523. https://doi.org/10.1016/j.jlp.2011.03.004
[8] Mardani, A., Jusoh A. and Zavadskas, E.K. (2015). Fuzzy multiple criteria decision-making techniques and applications-Two decades review from 1994 to 2014, Expert systems with applications, 42, 4126-4148. https://doi.org/10.1016/j.eswa.2015.01.003
[9] Marhavilas, P. K. and Koulouriotis, D. E. (2008). A risk-estimation methodological framework using quantitative assessment techniques and real accidents’ data: Application in an aluminium extrusion industry, Journal of Loss Prevention in the Process Industries, 21, 596-603. https://doi.org/10.1016/j.jlp.2008.04.009
[10] Lang, L., and Fu-Bao, Z. (2010). A comprehensive hazard evaluation system for spontaneous combustion of coal in underground mining, International Journal of Coal Geology, 82, 27–36. https://doi.org/10.1016/j.coal.2010.01.014
[11] Badri, A., Nadeau, S. and Gbodossou, A. (2013). A new practical approach to risk management for underground mining project in Quebec, Journal of Loss Prevention in the Process Industries, 26, 1145-1158. https://doi.org/10.1016/j.jlp.2013.04.014
[12] Mahdevari, S., Shahriar, K. and Esfahanipour, A. (2014). Human health and safety risks management in underground coal mines using fuzzy TOPSIS, Science of The Total Environment, 488, 85-99. https://doi.org/10.1016/j.scitotenv.2014.04.076
[13] Verma, S. and Chaudhri, S. (2014). Integration of fuzzy reasoning approach (FRA) and fuzzy analytic hierarchy process (FAHP) for risk assessment in mining industry, Journal of Industrial Engineering and Management, 7, 1347-1367. http://dx.doi.org/10.3926/jiem.948
[14] Javadi, M., Saeedi, G. and Shahriar, K. (2017). Fuzzy Bayesian Network Model for Roof Fall Risk Analysis in Underground Coal Mines, Journal of Applied Sciences, 17, 103-115. https://scialert.net/abstract/?doi=jas.2017.103.115
[15] Samantra, C., Datta, S. and Mahapatra, S. S. (2017). Analysis of occupational health hazards and associated risks in fuzzy environment: a case research in an Indian underground coal mine, International Journal of Injury Control and Safety Promotion, 24, 311-327. https://doi.org/10.1080/17457300.2016.1178298
[16] Gul, M. and Ak, M. F. (2018). A comparative outline for quantifying risk ratings in occupational health and safety risk assessment, Journal of Cleaner Production, 196, 653-664. https://doi.org/10.1016/j.jclepro.2018.06.106
[17] Oz, N. E., Mete, S., Serin, F. and Gul, M. (2018). Risk assessment for clearing and grading process of a natural gas pipeline project: An extended TOPSIS model with Pythagorean fuzzy sets for prioritizing hazards, Human and Ecological Risk Assessment: An International Journal, 25, 1615-1632. https://doi.org/10.1080/10807039.2018.1495057
[18] Bakhtavar, E. and Yousefi, S. (2018). Assessment of workplace accident risks in underground collieries by integrating a multi-goal cause-and-effect analysis method with MCDM sensitivity analysis, Stochastic Environmental Research and Risk Assessment, 32, 3317-3332. https://doi.org/10.1007/s00477-018-1618-x 
[19] Shi, S., Jiang, B. and Meng, X. (2018). Assessment of gas and dust explosion in coal mines by means of fuzzy fault tree analysis, International Journal of Mining Science and Technology, 28, 991-998. https://doi.org/10.1016/j.ijmst.2018.07.007
[20] Gul, M., Guneri, A. F. and Nasirli, S. M. (2019). A fuzzy‑based model for risk assessment of routes in oil transportation, International Journal of Environmental Science and Technology, 16, 4671-4686. https://doi.org/10.1007/s13762-018-2078-z
[21] Huang, D., Li, W., Chang, X. and Tan, Y. (2019). Key factors identification and risk assessment for the stability of deep surrounding rock in coal roadway, International Journal of Environmental Research and Public Health, 16, 1-15. https://doi.org/10.3390/ijerph16152802
[22] Dong, G., Wei, W., Xia, X., Wozniak, M. and Damasevicius, R. (2020). Safety risk assessment of a Pb-Zn Mine based on Fuzzy-Grey correlation analysis, Electronics, 9, 1-18. https://doi.org/10.3390/electronics9010130
[23] Petrovic, D. V., Tanasijevic, M., Stojadinovic, S., Ivaz, J. and Stojkovic, P. (2020). Fuzzy model for risk assessment of machinery failures, Summetry, 12, 1-26. https://doi.org/10.3390/sym12040525
[24] Hwang, C.L. and Yoon, K. (1981). Multiple Attribute Decision Making, Methods and Applications A State-of-the-Art Survey, Springer-Verlag Berlin Heidelberg. https://www.springer.com/gp/book/9783540105589
[25] Alavai, I. and Rokny, H.A. (2011). Comparison of fuzzy AHP and fuzzy TOPSIS methods for plant species selection (case study: Reclamation plan of Sungun cooper mine, Iran), Australian journal of basic and applied sciences, 5, 1104-1113. http://www.ajbasweb.com/old/ajbas/2011/December-2011/1104-1113.pdf
[26] Chamzini, A.Y., Yakchali, S.H. and Zavadskas, E.K. (2012). Using an integrated MCDM model for mining method selection in presence of uncertainty, Economic Research-Ekonomska Istraživanja, 25, 869-904. https://doi.org/10.1080/1331677X.2012.11517537
[27] Ebrahimabadi, A. and Alavi, I. (2013). Plant type selection for reclamation of sarcheshmeh copper mine using fuzzy-topsis approach, Archives of mining sciences, 58, 953-968. https://doi.org/10.2478/amsc-2013-0067
[28] Kacprzak, D. (2018). Fuzzy TOPSIS method for group decision making, Multiple criteria decision making, 13, 116-132. 10.22367/mcdm.2018.13.07
[29] Kore, N.B., Ravi, K. and Patil, S.B. (2017). A simplified description of fuzzy TOPSIS method for multi-criteria decision making, International research journal of engineering and technology, 4, 1-4. https://www.irjet.net/archives/V4/i5/IRJET-V4I5548.pdf
[30] Nadaban, S., Dzitac, S. and Dzitac. I. (2016). Fuzzy TOPSIS: A general view, Procedia computer science, 91, 823-831. https://doi.org/10.1016/j.procs.2016.07.088
[31] Huang, W., Hossain, G.M.S., Sultana, A., Rasel, M. and Rahman, M.S. (2020). Applying Fuzzy Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) in the Selection of Best Candidate: A Case Study on Interview Performance, British Journal of Economics, Finance and Management Sciences, 17, 36-49. http://www.ajournal.co.uk/EFpdfs/EFvolume17(1)/EFVol.17%20(1)%20Article%204.pdf 
[32] Javanshirgiv, M., Moghadder, M.T. and Safari, M. (2017). The selection of appropriate mining method for the Deh Gheybi granite quarry mine using the FTOPSIS method, International journal of mining and mineral engineering, 8, 113-130. https://www.inderscience.com/offer.php?id=84203
[33] Javanshirgiv, M. and Safari, M. (2017). The selection of an underground mining method using the fuzzy TOPSIS method: a case study in the Kamar Mahdi II fluorine mine, Mining science, 24, 161-181. https://doi.org/10.5277/msc172410 
[34] Kumar, S., Singh, B., Qadri, M.A., Kumar, Y.V.S. and Haleem, A. (2013). A framework for comparative evaluation of lean performance of firms using fuzzy TOPSIS, International Journal of productivity and quality management, 11, 371-392. 10.1504/IJPQM.2013.054267
[35] Lashgari, A., Chamzini, A.Y., Fouladgar, M.M., Zavadskas, E.K., Shafiee,  and Abbate, N. (2012). Equipment selection using fuzzy multi criteria decision making model: Key study of Gole Gohar iron mine, Inzinerine Ekonomika-Engineering Economics, 23, 125-136. https://doi.org/10.5755/j01.ee.23.2.1544 
[36] Sitorus, F., Cilliers, J.J. and Brito-Parada, P.R. (2019). Multi-criteria decision making for the choise problem in mining and mineral processing: Applications and trends, Expert systems with applications, 121, 393-417. https://doi.org/10.1016/j.eswa.2018.12.001 
[37] Staletovic, N., Kovacevic, S. and Kovacevic, M. (2014). Development the model of assessment the OH&S risks for the work place driller in the process of geological exploratory drilling, Journal Mining & Metallurgy Engineering Bor, 3, 105-122. https://irmbor.co.rs/en/journal/mining-and-metallurgy-engineering-bor-en/
[38] Kusumawardani, R.P. and Agintiara, M. (2015). Application of fuzzy AHP-TOPSIS method for decision making in human resource manager selection process, Procedia computer science, 72, 638-464. https://doi.org/10.1016/j.procs.2015.12.173
[39] Sun, C.C. (2010). A performance evaluation model by integrating fuzzy AHP and fuzzy TOPSIS methods, Expert systems with applications, 37, 7745-7754. https://doi.org/10.1016/j.eswa.2010.04.066
[40] Trajkovski, L. (2010). Teskite telesni povredi i smrtni slucaevi pri rabota vo rudnicite vo R. Makedonija vo periodot od 1992 do 2009 godina, IV-to sovetuvanje na tema: Tehnologija na podzemna eksploatacija na mineralni surovini (PODEKS 2010), 4, 129-135.
[41] Trajkovski, L. (2010). Nesrekite permanentna pojava vo rudnicite vo Republika Makedonija, Makedonsko rudarstvo i geologija, 18, 34-37.